Stryker Robotics

SMC had the privilege of working on the Stryker Robotics Project and their cutting-edge R&D facility at Meridian Business Campus, Weston. The state-of-the-art space includes offices, labs, robotic zones, production areas, showrooms, a gym, and a commercial kitchen.

We were tasked with air conditioning the 4,921,000 cubic feet structure with 124 independently temperature-controlled zones. This was accomplished by installing (2) 275-ton air-cooled chillers, (8) AHUs, (3) CHW pumps, (124) VAVs, (11) DX systems, (12) EF, almost 6,600,000 linear feet of duct, and around 2,000 linear feet of CHW piping. SMC ensured seamless installation and testing of all HVAC equipment and ductwork, contributing to a successful project.

Project Timeline: July 2019 – May 2021